MLCP AERO MALL CIVIL WORKS
MLCP AERO MALL CIVIL WORKS
Client: Pebbles Infra-Tech Pvt. Ltd.
Duration: 6 Months
Executed diverse civil works including
brickwork, plastering, tiling, 18mm &
40mm granite fixing, and paver block
installations. Delivered 8,000 sq.ft of
Croma Store flooring in a single night,
completed Zudio Store and Food
Court flooring, and constructed the
compound wall. Delivered on time
with superior workmanship and client
satisfaction.
Client: Unique Associates
Area: 75,680 sq.ft
Duration: 3 Months
Upgraded terminal flooring by removing
existing tiles and installing 18mm granite.
Despite daily passenger operations,
31,850 sq.ft was completed in 45 days
through night shifts (11:00 PM – 5:00
AM), while the remaining 43,830 sq.ft
was finished during runway closure.
Completed within the stipulated time,
maintaining exceptional quality and
coordination